A can complete a work in 13 days and B in 20 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 13 days and B in 20 days. If they work together, the work will be completed in:
A. 12.88
B. 22.88
C. 17.88
D. 7.88
Answer: Option D
Solution (By JKExamLibrary)
Combined rate = 1/13 + 1/20. Required time = 7.88 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
29 men can complete a work in 32 days. If 37 men work at the same rate, how many days are required?
A. 27.58
B. 30.08
C. 32.58
D. 25.08

Correct Answer: Option D


Explanation:
Total work = 928 man-days. Days = 25.08.

This question belongs to: Maths Time and Work
Question #2 Report Error
14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in:
A. 24.16
B. 29.16
C. 34.16
D. 19.16

Correct Answer: Option D


Explanation:
Total work = 364 man-days. Time = 364/19 = 19.16 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
21 men can complete a work in 18 days. If 26 men work at the same rate, the work will be completed in:
A. 29.54
B. 24.54
C. 14.54
D. 19.54

Correct Answer: Option C


Explanation:
Total work = 378 man-days. Time = 378/26 = 14.54 days.

This question belongs to: Maths Time and Work