A can complete a work in 14 days and B in 12 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 14 days and B in 12 days. If they work together, the work will be completed in:
A. 21.46
B. 6.46
C. 16.46
D. 11.46
Answer: Option B
Solution (By JKExamLibrary)
Combined rate = 1/14 + 1/12. Required time = 6.46 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. In how many days can A alone complete the work?
A. 30 days
B. 40 days
C. 24 days
D. 20 days

Correct Answer: Option A


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing these gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6. Efficiency of A = (A+B+C) - (B+C) = 6 - 4 = 2. Time taken by A alone = 60 / 2 = 30 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
15 men can complete a work in 23 days. If 23 men work at the same rate, how many days are required?
A. 17.5
B. 15.0
C. 20.0
D. 22.5

Correct Answer: Option B


Explanation:
Total work = 345 man-days. Days = 15.0.

This question belongs to: Maths Time and Work
Question #3 Report Error
If 3 men or 5 women can do a piece of work in 12 days, in how many days will 6 men and 5 women complete the same work?
A. 5 days
B. 3 days
C. 6 days
D. 4 days

Correct Answer: Option D


Explanation:
3 Men = 5 Women => 6 Men = 10 Women. 6 men + 5 women = 10 women + 5 women = 15 women. Since 5 women take 12 days, 15 women will take (5 * 12) / 15 = 60 / 15 = 4 days.

This question belongs to: Maths Time and Work