A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work? MCQ with Answer and Explanation

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work?
A. 11 days
B. 10 days
C. 12 days
D. 9 days
Answer: Option A
Solution (By JKExamLibrary)
Total work = LCM(25, 20) = 100 units. Efficiency of A = 4, B = 5. Combined efficiency = 9 units/day. In 5 days, work done = 5 * 9 = 45 units. Remaining work = 100 - 45 = 55 units. Time taken by B to complete remaining work = 55 / 5 = 11 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days will A and B together complete the work?
A. 24 days
B. 35 days
C. 25 days
D. 30 days

Correct Answer: Option D


Explanation:
A's 10-day work = 10/80 = 1/8. Remaining work = 7/8. B completes 7/8 work in 42 days, so B completes full work in 42 * (8/7) = 48 days. Combined 1-day work = 1/80 + 1/48 = (3 + 5)/240 = 8/240 = 1/30. They finish together in 30 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can complete a work in 20 days and B in 36 days. If both work together, in how many days will the work be completed?
A. 20.36
B. 17.86
C. 15.36
D. 12.86

Correct Answer: Option D


Explanation:
Combined rate = 1/20 + 1/36. Time = 12.86 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A and B can complete a work in 15 days and 10 days respectively. They started the work together but B left after 2 days. In how many days will A complete the remaining work?
A. 11 days
B. 10 days
C. 8 days
D. 9 days

Correct Answer: Option B


Explanation:
Total work = LCM(15, 10) = 30 units. Efficiency of A = 2, B = 3. Combined efficiency = 5 units/day. In 2 days, work completed = 2 * 5 = 10 units. Remaining work = 30 - 10 = 20 units. Time taken by A to complete remaining work = 20 / 2 = 10 days.

This question belongs to: Maths Time and Work