A can do a work in 11 days and B in 29 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 11 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 10.98
B. 8.48
C. 13.48
D. 5.98
Answer: Option D
Solution (By JKExamLibrary)
Combined time for full work multiplied by 0.75 = 5.98 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
A can complete a piece of work in 12 days and B in 15 days. They work together for 3 days and then B leaves. In how many days will A complete the remaining work?
A. 7.5 days
B. 5.6 days
C. 4.8 days
D. 6.6 days

Correct Answer: Option D


Explanation:
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. Combined efficiency = 9 units/day. In 3 days, work completed = 3 * 9 = 27 units. Remaining work = 60 - 27 = 33 units. Time taken by A to complete remaining work = 33 / 5 = 6.6 days.

This question belongs to: Maths Time and Work
Question #2 Report Error
8 men can complete a work in 24 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 16.0
B. 18.0
C. 20.0
D. 22.0

Correct Answer: Option A


Explanation:
Total work = 8 × 24 = 192 man-days. Required days = 192/12 = 16.0 days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can complete a work in 23 days and B in 28 days. If both work together, in how many days will the work be completed?
A. 15.13
B. 17.63
C. 20.13
D. 12.63

Correct Answer: Option D


Explanation:
Combined rate = 1/23 + 1/28. Time = 12.63 days.

This question belongs to: Maths Time and Work