If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same work? MCQ with Answer and Explanation

If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same work?
A. 5 days
B. 2 days
C. 4 days
D. 3 days
Answer: Option D
Solution (By JKExamLibrary)
3 Men = 6 Women => 1 Man = 2 Women. 12 Men + 8 Women = 12(2 Women) + 8 Women = 32 Women. If 6 women do it in 16 days, then 32 women do it in (6 * 16) / 32 = 3 days.

This question belongs to: Maths Time and Work

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1 Report Error
21 men can complete a work in 29 days. If 29 men work at the same rate, how many days are required?
A. 26.0
B. 21.0
C. 23.5
D. 28.5

Correct Answer: Option B


Explanation:
Total work = 609 man-days. Days = 21.0.

This question belongs to: Maths Time and Work
Question #2 Report Error
A can do a piece of work in 40 days. He works at it for 8 days and then B finishes it in 16 days. How long will A and B together take to complete the work?
A. 25 days
B. 15 days
C. 13(1/3) days
D. 20 days

Correct Answer: Option C


Explanation:
Let total work be 40 units. Efficiency of A = 1 unit/day. In 8 days, A completes 8 units. Remaining work = 40 - 8 = 32 units. B finishes 32 units in 16 days, so B's efficiency = 32 / 16 = 2 units/day. Combined efficiency of A and B = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work
Question #3 Report Error
A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work?
A. 11 days
B. 9 days
C. 10 days
D. 12 days

Correct Answer: Option A


Explanation:
Total work = LCM(25, 20) = 100 units. Efficiency of A = 4, B = 5. Combined efficiency = 9 units/day. In 5 days, work done = 5 * 9 = 45 units. Remaining work = 100 - 45 = 55 units. Time taken by B to complete remaining work = 55 / 5 = 11 days.

This question belongs to: Maths Time and Work